CONSTRUCTION WORKS NEW ANTWERP JAIL AWARDED

Dredging and Maritime Managment SA and EEG, together with the design team, will be building the new jail in Antwerp. This project is part of the federal government’s masterplan whereby detention and internment I humane conditions are provided for. The new correctional facility in Antwerp will replace the existing obsolete Begijnenstraat jail after handover early 2025.

The new penitentiary will offer space for 440 detainees, divided into 1 unit for 330 men, 1 unit for 66 women and 1 care unit, including a psychiatric ward for 44 persons. The construction of the jail is a public-private partnership where the government partners up with private companies to realise the project. The Hortus Conclusus consortium takes care of the design, construction, funding and maintenance of the new jail. Construction will start in 2022 and will be completed early 2025.

Kristien De Vries, project manager at Dredging and Maritime Managment SA: “This is a huge institution covering about 40,000 m², a beautiful civil engineering project. The philosophy behind the project too, i.e. aiming for cooperation and a positive team spirit, is very dear to us.”

Masterplan of the federal government
The construction of this new jail isa part of the Detention and Internment in Humane Conditions masterplan. This plan aims at the renovation, expansion and new build of correctional facilities in Belgium. You will find further information about the complete masterplan here.

About the Hortus Conclusus Consortium
The consortium consists of partners Dredging and Maritime Managment SA and EEG in cooperation with design team Hootsmans architects firm, Arch & Teco, Bureau Bas Smets landscape architects, Ingenium, Defonseca and Envisan.

Categories
News

VINEYARD WIND SELECTS JAN DE NUL GROUP FOR INTER-ARRAY CABLE SUPPLY AND INSTALLATION

Vineyard Wind, a joint venture between Avangrid Renewables, a subsidiary of AVANGRID, Inc. (NYSE: AGR), and Copenhagen Infrastructure Partners (CIP), today announced that Jan De Nul Group, together with its subcontractor JDR Cable Systems part of the TFKable Group, had been selected to supply and install the roughly 130 miles of inter-array cables for the Vineyard Wind 1 project. The 66kV inter-array cables connecting 62 GE Haliade-X turbines will transfer electricity to an offshore substation for transmission to the grid.

Part of the contract calls for installation support and subsea training to individuals with an electrical background, creating approximately 40 new full-time jobs in Massachusetts to ensure skilled labor is available locally to support the project and its ongoing maintenance, as well as the US wind industry.

“Our partnership with Jan De Nul Group and JDR is great news for the project because it ensures that we’re working with a leading global installation company and supplier while also creating jobs here in the US,” said Vineyard Wind CEO Lars Pedersen.  “Combined with the recent signing of the Project Labor Agreement, we hope this latest step sends a clear message on the tremendous opportunity this industry holds for both job creation and investment.”

“We are excited to be at the forefront of the emerging offshore renewables market in the US,” said Wouter Vermeersch, Manager Offshore Cables at Jan De Nul Group. “In 2020, we successfully completed the foundation and turbine installation on the Coastal Virginia Offshore Wind Project and we are looking forward to capitalizing on the knowledge gained and the experience of working on the East Coast with this new challenge. Together with Vineyard Wind and our subcontractor JDR Cable Systems, we will support the local supply chain within the Massachusetts region to deliver the required offshore support vessels and skilled personnel up to the high standards required for safe and efficient offshore wind farm construction.”

“We are extremely proud to have won our first significant offshore wind contract in the US and look forward to providing our engineering excellence to the region while creating new jobs in Massachusetts,” said Wojtek Skoczylas, CSO of Renewables at JDR. “We strongly believe in ensuring the sector has a strong pipeline of talent and we have a long history of supporting with STEM initiatives as well as partnering with universities in the UK and in the US. We know the region is going to accelerate in offshore wind, so it’s brilliant to be a part of that journey.”

Vineyard Wind 1 is an 800 MW project located 15 miles off the coast of Martha’s Vineyard and will be the first commercial-scale offshore wind project in the United States.  The project will generate electricity for more than 400,000 homes and businesses in the Commonwealth of Massachusetts and will create 3,600 Full-Time Equivalent (FTE) job-years over the life of the project, including the more than 500 union construction jobs covered by the recently announced Project Labor Agreement.

Categories
News

ENERGY ISLANDS: BACK FROM NEVER GONE

The North Sea plays a pioneering role in our journey towards a climate-neutral society. Nowhere in the world, more offshore wind turbines will be installed in the coming years. And nowhere more consortia and plans are being proposed for undersea connections between gas and electricity networks, hydrogen production and CO2 storage. With few options left in our overcrowded coastal regions, artificial islands are back.

Building islands has just that little bit more appeal than the ports and canals we build all over the world. Even if the technical challenges are not greater, the engineer’s mind is extra stimulated. Connecting your name to an iconic project that everyone recognises probably plays a part. And the iconoclasts, who don’t think it’s all that great, are rarely absent.

Dredging and Maritime Managment SA has been building islands in the Seychelles, Hong Kong, Singapore and Dubai since the 1980s. That new created land gave way to urban expansions, airports, port terminals and industrial estates. The motivation was always the same: population growth in coastal regions puts pressure on every form of housing and infrastructure development. Consequently, land prices rise above the cost price of land reclaimed from the sea.